The countdown is on! Only two months to go until the completion of our new state-of-the-art hybrid finishing line for technical threads.
Construction work at our plant in Hessisch Lichtenau continues to progress rapidly.
The following progress has already been made this year:
- Completion of the steel construction work
- Installation of the dip stations
- Connection of the thermal oil piping to the existing thermal oil system and to the new regenerative post-combustion plant
- Cold commissioning of the system has started
- Pipework for the ventilation technology in the hall
- Installation of the heating is in full swing
The first trial production runs will start as planned in April.
You can find detailed information on the investment project in our previous NEWS articles:
- Contribution from 02.12.2022 – Construction activities of the hybrid equipment system | Hessisch Lichtenau
- Article from 15.12.2021 – Construction progress of the new production hall | Hessisch Lichtenau
- Article from 19.10.2021 – Ground-breaking ceremony for new production hall in Hessisch Lichtenau