Hybrid equipment plant – construction progress | Hessisch Lichtenau

The countdown is on! Only two months to go until the completion of our new state-of-the-art hybrid finishing line for technical threads.
Construction work at our plant in Hessisch Lichtenau continues to progress rapidly.

The following progress has already been made this year:

  • Completion of the steel construction work
  • Installation of the dip stations
  • Connection of the thermal oil piping to the existing thermal oil system and to the new regenerative post-combustion plant
  • Cold commissioning of the system has started
  • Pipework for the ventilation technology in the hall
  • Installation of the heating is in full swing

The first trial production runs will start as planned in April.